Projects
HAWAIʻI LAND & POWER's projects, as facts: name, island, technology, capacity, status, the procurement or docket each sits in, and the counterparty. Schedules are not published.
Current Projects Under Development
| Project | Island | Technology | Capacity | Status | Procurement or docket | Counterparty |
|---|---|---|---|---|---|---|
| Harborside Generating Station | Oʻahu | Dual-fuel reciprocating engines | 88.51 MW | In development | Hawaiian Electric Integrated Grid Planning RFP, Docket No. 2024-0258 | Hawaiian Electric Company |
| Alahao Firm Generation | Hilo, Hawaiʻi Island | Dual-fuel reciprocating engines | 30 MW | In development | Hawaiian Electric Integrated Grid Planning RFP, Docket No. 2024-0258 | Hawaii Electric Light Company |
| Alahao Energy Storage | Hilo, Hawaiʻi Island | Battery energy storage | 20 MW / 120 MWh | In development | Hawaiian Electric Integrated Grid Planning RFP, Docket No. 2024-0258 | Hawaii Electric Light Company |
| Kauaʻi Integrated Waste Processing Facility | Kauaʻi | Municipal solid waste processing with renewable fuel production and energy recovery | ≈100,000 tons of MSW per year | In development | County of Kauaʻi XRFP No. 2025-XRFP-4, Technology for Long-Term Management of Municipal Solid Waste | County of Kauaʻi |
Status: In development · Selected · Under contract · Operating · Prior role
Harborside Generating Station
Harborside Generating Station is an 88.51 MW firm generation project on Oʻahu, proposed in Hawaiian Electric's Integrated Grid Planning RFP. HL&P first proposed the site in the Stage 3 RFP in 2023. The engine basis is Wärtsilä dual-fuel reciprocating engines.
Alahao Firm Generation and Alahao Energy Storage
Alahao Firm Generation is a 30 MW firm generation project, and Alahao Energy Storage a 20 MW / 120 MWh battery storage project, on a Department of Hawaiian Home Lands industrial parcel at Panaʻewa, adjacent to Hawaii Electric Light's Kanoelehua substation, under a right-of-entry the Hawaiian Homes Commission approved in February 2025. The engine basis is Wärtsilä dual-fuel reciprocating engines.
Kauaʻi Integrated Waste Processing Facility
In the County of Kauaʻi's two-step procurement, 2025-XRFP-4, HL&P leads the development team, with Mālama One Recycling, for a facility that would process the County's municipal solid waste and make renewable diesel and naphtha from it.
Prior Roles
| Project | Island | Technology | Capacity | Status | Procurement or docket | Counterparty |
|---|---|---|---|---|---|---|
| Puʻuloa Energy and Puʻuloa Solar | Oʻahu | Renewable firm generation; solar with storage | 99 MW; 6 MW / 24 MWh | Ameresco projects; HL&P development partner | Stage 3 RFP, Docket No. 2017-0352; Puʻuloa Solar PPA approved in Docket No. 2025-0436 | Hawaiian Electric Company |
| Hu Honua Bioenergy | Hawaiʻi Island | Biomass generation | 23.5 MW | Prior role of HL&P's Principal: acquired the plant from C. Brewer in May 2005, performed the initial refurbishment assessment, negotiated with Hawaii Electric Light Company to restart it as a qualifying facility, and sold a majority interest in 2008. | — | Hawaii Electric Light Company |
— : not yet published.
The people who carry the work. Team